Turbine Inlet Air Cooling of two MGT80 at South-II CCPP

Client: MAPNA Group

Plant Owner: Mobarakeh Steel co.

Location: Isfahan, Iran.

Project Duration: 9 Month

Scheduled Commissioning Date: Aug. 2023

Scope Of Work: EPC of Upstream Media Cooling system for two MGT80 GTs, each one with nominal Power of 308MW.

Status: under construction

.

.

Keywords:

Upstream Media Cooler, Upstream Evaporative cooler, Upstream system, Media Cooler, Turbine Inlet Air Cooling system , TIAC, GTIAC, Turbine Cooling, مدخل تبريد الهواء التوربيني, التبريد التبخيري للتوربينات, التبريد المنبع للتوربينات