Upstream Inlet Air Cooling System for Rumaila Power Plant,Iraq

Client: MAPNA Group

Plant Owner: Shamara Holding

Location: Basra, Iraq

Project Duration: 6 Month

Commissioning Date: June 2023

Scope Of Work: EPC of Upstream Media Cooling system for two MGT70 GTs, each one with nominal Power of 185MW.

Status: PAC

Power increase: more than 18% on each GT @ design conditon

.

.

Keywords:

Upstream Media Cooler, Upstream Evaporative cooler, Upstream system, Media Cooler, محطة كهرباء الرميلة, Turbine Inlet Air Cooling system , TIAC, GTIAC, Turbine Cooling, مدخل تبريد الهواء التوربيني, التبريد التبخيري للتوربينات, التبريد المنبع للتوربينات